Blog Archive

Monday, December 15, 2025

Record Power Project Cancellations in the U.S. Amid Record Demand Growth: Led by Trump Administration Cuts, Tariffs, Public Opposition to Projects, Including Data Centers, Interconnection Queue Cleanup, and Lackluster Transmission Buildout


     A new report by Cleanview tabulates power project cancellations in 2025, with nearly 2000 projects cancelled this year. The report cites 1,891 power project cancellations amounting to 266 GW in generation capacity (as always, I hate to use capacity as a metric due to the low capacity factors of wind and solar compared to fossil and nuclear). 93% of those cancellations were clean energy projects, which include wind, solar, and battery projects. The report also notes that public opposition against projects, as well as against data centers and transmission lines, is a big factor as well.




     Seeking Alpha reports that the failure to build transmission lines has grown, despite an immense need for more power transmission. I found the following statement from the Cleanview report shocking:

The failure to build transmission lines has led to high interconnection costs, the report said, as high-voltage transmission construction plummeted from 4,000 miles in 2013 to 322 miles in 2024; Louisiana and Missouri, where interconnection costs now exceed $900,000 per MW, lost a combined 26 GW of capacity in 2025.”

     They also note the significant effects of “battery cannibalization,” strongly affecting battery project profitability in high deployment areas like Texas and California. In addition, they note that Trump tariffs have raised the cost of battery deployment considerably.

"Battery cannibalization" - where growing capacity drives down the prices batteries earn - has made it harder to build profitable battery projects; Clearview noted Texas battery revenues plunged 70% from $192/kW in 2023 to $55/kW in 2024, and California battery revenues fell from $103/kW in 2022 to $53/kW in 2024, while President Trump's tariffs have raised the cost of batteries by 56%-69%.”

     They note that 26.5 GW of cancellations are due to Trump’s direct cancellation of offshore wind projects. The Trump administration has also said that growing power demand will require 100 GW of new capacity, with much of that expected to come from natural gas. Unfortunately, higher prices for power consumers seem unavoidable. This annoys me!  

     The report summarizes:

Electricity demand is growing faster than it has in decades in the United States. Data centers, manufacturing reshoring, and electrification are driving massive growth in power consumption. But at the exact moment America needs more electricity generation, the country's infrastructure developers are canceling projects at an alarming rate.”

     A further summary within the executive summary of the report is given below.




     The last section of the summary above does show that a significant number of cancellations do come from interconnection queue cleanup to remove speculative projects in an attempt to streamline and improve the interconnection process and remove unnecessary projects. The cleanups have been successful at removing speculative projects, so that can be seen as a success. This will help the regional power interconnections to focus more on viable projects and should, theoretically, speed up timelines to full project development and completion.

     Public opposition is cited as a powerful force, affecting projects. The report notes that in Virginia, a hub of data center development with a fair solar endowment, more solar projects are being denied than approved. Public opposition in the state is high.

The severity of local opposition extends beyond individual permit denials. At least 10 Virginia counties have enacted outright bans or severe restrictions on solar, with Mecklenburg County—the state's ninth-largest county—passing an ordinance in April 2025 that removed utility-scale solar as an allowed land use entirely.”




     Indiana, and my state, Ohio, are also leading opposition to clean energy projects.

     Energy writer Robert Bryce has tracked public opposition with his database of rejections for clean energy projects. He is now documenting the growing rate of AI data center rejections due to land-use conflicts. Opposition to data centers also includes significant and legitimate concerns about water use. I plan to write about this soon, as different water use issues are cropping up where data centers are in operation and where they are being built. He notes that the reasons for opposition to data centers are similar to those for wind and solar, aside from water use issues. These include “property values, water usage, electricity costs, and deep distrust of big business in general and Big Tech in particular.” He also notes that Big Tech plans to spend $375 billion this year and $500 billion next year on data center buildout, which means these issues will continue and probably grow a bit more.




     The report also notes that the lack of power transmission buildout is leading to higher interconnection costs, which is also killing projects.

The consequences for renewable energy developers have been severe. In MISO, the South and Midwest's grid operator, the average interconnection cost for canceled projects in the latest study cycle was $753,116 per MW—roughly 50% of a typical solar or wind project's total capital expenditure.”

     In MISO, the highest interconnection costs correlate to the most cancellations.




     The following statement from the report reflects the problem that Cleanview CEO Michael Thomas notes is underinvestment in transmission, which creates bottlenecks. This is a problem in several regions, including PJM.

Decades of underinvestment in transmission infrastructure have created a massive bottleneck. Developers can't afford to build projects when grid connection costs equal or exceed the cost of the generation equipment itself. Until transmission buildout accelerates, interconnection costs will continue forcing economically viable projects out of the queue, threatening America's ability to meet growing electricity demand.”

     Returning to the battery cannibalization problem, he notes that it has led to significant revenue decline and is responsible for 30% of battery project cancellations:

Ancillary service prices fell from $21 per megawatt-hour in 2023 to $5/MWh in 2024 and are currently at $3/MWh. Analysts at McKinsey estimate that battery cannibalization—where growing battery capacity drives down peak hour prices—is responsible for at least 30% of the observed revenue decline. Profitability among battery operators now depends more on strategic site selection and operational timing rather than fleet size, with most major operators posting year-to-date profitability below 2.2%.”

     It is also noted that tariffs have led to “dramatically higher construction costs.” The Trump administration’s Foreign Entity of Concern (FEOC) regulations, set to go into effect in 2026, are expected to further increase project costs as well as complexity.

Projects that penciled at $192/kW in revenue with $100/kWh battery costs in 2023 now face $55/kW in revenue with $130/kWh costs—a fundamental shift that has forced developers to cancel 79 GW of planned capacity nationwide.”

     The offshore wind cuts, some to projects well underway, have created lots of problems for wind developers and for the states that host them.

     Thomas cites policy incoherence as a barrier to solving these problems that need to be solved.

The current trajectory is unsustainable. America is adding unprecedented electricity demand while canceling the generation capacity needed to meet it. Counties are approving gigawatt-scale data centers while rejecting solar projects—sometimes on the same night. States are courting hyperscalers while blocking the energy projects that would power them. The federal government is promoting "energy dominance" while halting construction and imposing prohibitive tariffs. This policy incoherence threatens grid reliability, consumer affordability, and America's competitiveness in the global AI race.”

 


References:

 

Developers have canceled nearly 2,000 power projects this year – report. Seeking Alpha. December 13, 2025. Developers have canceled nearly 2,000 power projects this year - report

Report: Developers Have Cancelled 1,891 Power Projects in 2025: An analysis of US power projects that have been cancelled in 2025. Michael Thomas. Cleanview. Developers Have Cancelled 1,891 Power Projects in 2025

The Data Center Backlash Is Global. Robert Bryce. Substack. December 10, 2025. The Data Center Backlash Is Global - Robert Bryce

 

 

No comments:

Post a Comment

      Art Berman is a legendary oil & gas expert. People listen to what he says. Now, he says enhanced geothermal systems (EGS) are seri...