A huge sewage and wastewater spill, possibly the largest in U.S. history, spilled toxic sewage into the Potomac River. DC Water reported that on January 19, there was a collapse in a section of the Potomac Interceptor located along the Clara Barton Parkway at the 495 interchange and C & O Canal National Historical Park.
According to DC Water:
“Based on flow monitoring data collected before and
after interim bypass pumping was activated, DC Water estimates that
approximately 243 million gallons of wastewater has overflowed from the
collapse site. The vast majority of this volume, approximately 194 million
gallons, occurred within the first five days, prior to the overflows being
significantly reduced through bypass pumping operations.”
“Efforts to reach the collapse site and finalize the repair
strategy remain challenging due to the discovery of a rock dam inside the
interceptor, which is significantly restricting internal access. DC Water is
implementing a revised construction and repair approach that is expected to
take 4-6 weeks and includes:
· Construction
of a new bypass pump location to enable the safe removal of rock at the
collapse site.
· Creation
of a new upstream access point to facilitate repairs and enhance worker safety.
· Development
of a new downstream connection to the Potomac Interceptor to improve wastewater
conveyance and reduce future risk.
· Installation
of an upstream bulkhead to restrict wastewater flow to the damaged section as
much as possible.”
“In the interim, the existing bypass system remains
operational and is successfully diverting wastewater around the damaged pipe
section and back into the Potomac Interceptor. Some limited overflows have
occurred, primarily due to increased wastewater flow associated with snowmelt
and brief pump maintenance and operational issues. For example, during
overnight pump maintenance, up to 300 gallons of wastewater escaped but was
contained and did not reach the Potomac River.”
“Until full functionality is restored to the Potomac
Interceptor, there remains a residual risk of additional limited
overflows. However, both the likelihood and volume of any future
releases are expected to remain minimal.”
Early water testing showed extremely high levels of E. Coli.
They report that there have
been no significant overflows since the connector was successfully bypassed.
Water testing is occurring daily. They reached the collapsed sewer line section
on February 19, a month after the spill. It is a slow process. First, the
wastewater had to be blocked off and rerouted through the bypass. Then, a way
to access the damaged section had to be devised.
Water testing by the
University of Maryland School of Public Health found E. coli at
very high levels and Staphylococcus aureus, including its resistant
version known as MRSA, in the river. They also note:
“Up to 75,000 sewage overflows happen every year in the
United States, according to UMD’s Water Emergency Team (WET), exposing
residents to raw sewage, waterborne pathogens and possibly antibiotic-resistant
bacteria. The effects are serious, including illnesses such as bacterial
infections that can cause serious illness and death.”
DC Water reported that they
reached the damaged section after installing a steel bulkhead gate.
“Crews were able to reach the damaged pipe section,
after the successful installation of a steel bulkhead gate that is now blocking
all flow in the pipe. At the same time, the enhanced bypass pumping system is
fully operational and diverting wastewater around the collapse site and back
into the Potomac Interceptor further downstream. This critical step has enabled
workers to access the site safely and begin assessing the pipe for repairs. The
manual nature of this work underscores the complexity of the situation and the
debris at the collapse site must be removed to fully expose the pipe for
engineers to evaluate the damage inside.”
Trump recently weighed in on
the broken infrastructure, blaming it on Maryland Governor Wes Moore. However,
Moore pointed out that DC Water, who owns and operates the infrastructure, is
under federal jurisdiction. DC Mayor Muriel Bowser visited the site on February
19.
“Repairs are expected to be completed by mid-March,
restoring full flow and function to the Potomac Interceptor. At that point the
bypass pumping system utilizing the C & O Canal will no longer be
needed. Once the collapse site is cleared, work will begin to remove
a 30-foot rock dam blocking the pipe. Crews will need to proceed carefully not
to trigger another collapse, due to the uncertain integrity of the remaining
pipe.”
The Potomac Interceptor was
built in 1960 and is now 66 years old. The spill is perhaps an important
indicator that we need to pay more attention to aging infrastructure, although
underground pipes of any sort are difficult to monitor.
DC Water CEO David L. Gadis
summarized what happened in a February 11 post:
“On the evening of Monday, January 19, 2026, security
cameras detected unusual activity near one of our odor control facilities along
the Clara Barton Parkway. That alert led our teams to discover a collapse in a
section of the Potomac Interceptor sewer line, which resulted in an
uncontrolled overflow of wastewater into the Potomac River. From that moment
forward, DC Water crews and contractors mobilized around the clock - through
sub-freezing temperatures and severe winter weather - to contain the overflow,
protect public safety, and begin repairs to the 72-inch pipe. By January 24, an
emergency bypass was activated to reroute flows and stop the discharge.”
References:
Potomac
wastewater spill appears to be largest in US history. Tara Suter. The Hill.
February 12, 2026. Potomac wastewater spill appears to
be largest in US history
DC
Water’s Potomac Interceptor. Potomac Interceptor Project | DC Water
DC
Water Releases Key Findings on Extent of Sewer Overflow and Potomac River
Impact. DC Water. February 6, 2026. DC Water Releases Key Findings on
Extent of Sewer Overflow and Potomac River Impact | DC Water
An
open letter from DC Water CEO David L. Gadis about the Potomac Interceptor, DC
Water. February 11, 2026. An open letter from DC Water CEO
David L. Gadis about the Potomac Interceptor | DC Water
UMD
team finds E. coli, MRSA in Potomac River after sewage spill: Researchers find
extremely high levels of disease-causing bacteria including an
antibiotic-resistant strain, raising public health concerns. University of
Maryland. School of Public Health. February 5, 2026. UMD team finds E. coli, MRSA in
Potomac River after sewage spill | University of Maryland | School of Public
Health
DC
Water Reaches Collapsed Pipe Section; Damage Assessment Underway. DC Water. February
19, 2026.
UPDATE:
Potomac Interceptor Collapse, February 18. DC Water. February 18, 2026. UPDATE:
Potomac Interceptor Collapse, February 18 | DC Water

































