A special
report issued by Politico’s E&E News in May 2024 details some serious
issues around pipeline inspections done by pipeline developers. According to
the report, both flawed inspections and ignored warnings from inspectors have
resulted in disasters that could have been averted.
The issue of
self-regulation and whether and where it works is still unresolved. I think it
can work but if corners are cut and potential problems are ignored, or worse,
covered up, then it can become a big problem. The special report suggests that
is the case with developer-employed private pipeline inspectors. Presumably,
the inspectors provide reports for the pipeline developer and the developer
decides whether or not to act on them. Speaking as someone who has worked both
in a highly regulated industry and as a regulator, I can say self-regulation
can go either way. The goal of any regulator, whether public or private, should
be to get the facts correct about risks and act accordingly. Many companies
hire environmental firms to do compliance audits as a kind of pre-inspection to
prepare for inspections by state and federal agencies like EPA, OSHA, mine
safety, natural resources, and in this case pipeline safety: The Pipeline and
Hazardous Materials Safety Administration (PHMSA). These agencies do not have
the manpower to observe day-to-day construction. Thus, self-regulation must be
relied upon to a significant extent.
For pipelines
there is apparently some discrepancy about whose responsibility it is to ensure
pipeline safety as the following opinions from the article show:
“It’s the operator that’s responsible for making sure
that that work is being done correctly,” said Dave Murk, senior director of
midstream policy at the American Petroleum Institute, the industry’s main trade
group. “But ultimately, it’s PHMSA’s job, or state inspectors, to make sure
what’s been done by the operator and contractors is in accordance with the
regulations. The regulator is responsible for making sure it’s done safely.”
“But the regulators see it differently. Without
directly contradicting Murk, a PHMSA spokesperson said the agency’s position is
that the operator is “fully responsible” for compliance and safety.”
The companies
developing pipelines hire private inspectors who are supposed to ensure
day-to-day compliance. They represent the developer. PHMSA or state inspectors
only see what they can during their periodic inspections. Thus, the private
inspectors see far more of what is going on than the state or PHMSA inspectors.
But as inspectors, even though private, they still have a mandate to ensure
that the pipeline is built safely and in compliance with safety and
environmental rules. The state and PHMSA inspectors verify that as best they
can with more limited availability. PHMSA has about 200 inspectors and there
are about 450 inspectors in state-level agencies. In contrast, according to the
Interstate Natural Gas Association of America, there are about 8000 certified private
inspectors.
According to the report, flawed inspections resulted
in several preventable environmental tragedies:
“Oil spills in Kansas and damage to farms in Oklahoma
have been linked to flawed inspections. Inspection failures were cited by
federal investigators seeking a $40 million fine for the spilling of toxic
drilling fluid in Ohio. And on the Mountain Valley gas pipeline project in
Virginia and West Virginia, federal appeals court judges say inspectors “failed
to prevent” widespread erosion problems.”
Self-regulation can bring up conflict-of-interest
concerns. If the pipeline developer limits the power of the inspectors they
hire to make changes, as has been alleged, then that is a big concern. Of
course, one should probably not expect private inspectors to be as neutral
as government inspectors. Both could be biased. Some government inspectors may
be anti-fossil fuel advocates. Company-paid inspectors may be fossil fuel
advocates. We can’t really change personal biases.
The report recounts
a whistleblower who said he observed several avoidable mistakes that were not
corrected. The pipeline developer, Shell in this case, disputes this, but they
did receive misdemeanor criminal charges for several covered-up spills documented
by the whistleblower.
In the fall of
2017 while Energy Transfer Partners’ Rover pipeline was being built in Ohio,
horizontally drilling for the large diameter line under the Tuscarawas River
and adjacent wetlands resulted in a large amount of bentonite slurry being lost
underground in unconsolidated sediments or fractures and some resurfacing in
the wetlands. Further analysis showed that diesel fuel was added to the slurry.
The company had private inspectors for this horizontal drilling section, but
they failed to discover the fluid loss or the presence of diesel fuel in the
slurry. I wrote about this when it happened here.
I wrote that:
“ETP also added third-party independent inspectors for
the last horizontal/directional (HDD) drilling sites as a result of the new
FERC requirements. They also added an annular pressure tool to monitor pressure
changes in the annulus that might indicate fluid loss or reduced circulation.”
FERC concluded in their 2021 enforcement report that the
private inspectors working on the project were “untrained, lacked direction and
left powerless” and that ETP pressured inspectors and fostered a “corporate
culture that favored speed and construction progress over regulatory compliance.”
FERC also alleged that private inspectors on a Cheniere pipeline often failed
to note when post-construction land reclamation was inadequate.
Some pipelines, such as those supplying export
facilities, are inspected by FERC. These projects add a third layer of
inspectors, known as ‘compliance monitors’ who report to FERC but are paid as
contractors by the pipeline developer. It is a compromise of sorts, but it does
add a third layer of protection so to speak. FERC defends the compliance
monitors as impartial and says they work for FERC, even if paid by the
developer. It gives them the needed ‘eyes and ears’ on these geographically spread-out
projects. FERC also argues that their inspectors are very experienced and well-trained.
Another issue
is how the pipeline developer manages their own contractors on these projects.
ETP and Cheniere both argued that “rogue contractors” were responsible for
environmental issues, the added diesel fuel in ETP’s case and the poor land reclamation
in Cheniere’s case.
As for solutions, some argue for more money to
be spent far more government inspectors. Others want PHMSA to have their
inspectors in the field more. Enbridge wrote in 2021 about their Line 3 oil pipeline
replacement project in Minnesota which began transporting oil in October 2021:
“Enbridge will retain environmental inspectors (EIs)
during Project construction who will be responsible for understanding all
regulatory requirements and permit conditions, and ensuring that contractors
abide by these conditions. The project will also be supervised by third-party
environmental monitors who will report any concerns directly to appropriate
agencies.”
Thus, there are third-party monitors reporting any concerns to the regulating agencies. This should resolve a big chunk of conflict-of-interest concerns. When there are three layers of private, public, and third-party inspectors on these projects there should be less excuses for avoidable violations. I think that self-regulation can work in this way as an overlapping hybrid of compliance assurance.
References:
‘Everything’s
on fire’: Inside the nation’s failure to safeguard toxic pipelines. Mike
Soraghan. Politico. May 5, 2024. ‘Everything’s on fire’: Inside the
nation’s failure to safeguard toxic pipelines - POLITICO
Line 3
Replacement Project. Environmental Permitting. Enbridge. June 19, 2021. Environmental Permitting - Enbridge
Inc. (archive.org)
Unexpected
Drilling Fluid Releases Via 'Lost Returns' During Horizontal Drilling Under
Ohio Wetlands and Waterways in Constructing the Rover Pipeline: Operational and
Regulatory Issues. Kent Stewart. Blue Dragon Energy Blog. November 20, 2017. Blue Dragon Energy Blog: Unexpected
Drilling Fluid Releases Via 'Lost Returns' During Horizontal Drilling Under
Ohio Wetlands and Waterways in Constructing the Rover Pipeline: Operational and
Regulatory Issues
No comments:
Post a Comment