Sunday, February 26, 2023

The U.S. Power Grid’s Interconnection Process is a Gauntlet That Slows Down Wind, Solar, and Battery Projects: Transmission, Grid Integration Capabilities, Permitting, Supply Chains, and Oppositions are the Reasons Why

 

     The interconnection queue refers to the phase of an energy project from when the interconnection request is made to the power operator to the granting of an interconnection agreement. It is a proxy for the time it takes to begin construction of a project from when a request is made. But the vast majority don’t get built. The New York Times reports that now solar, wind, and battery projects are taking on average more than 3 years to get through interconnection queues and a whopping 80% of projects do not make it at all. It takes an average of a little over 4 years to get to commercial operation from interconnection request. In California’s CAISO it takes 5 years. Even though these projects can generally be built quickly and on budget, the time it takes to get them running is quite slow. Just a decade ago that length of time used to be two years, so it has doubled. Supply chain issues, permitting slowdowns, public opposition, and lack of adequate transmission or grid integration capabilities are the problems. The high number of projects that are withdrawn is actually nothing new. DOE data from Berkeley Labs shows that since 2000 the average number of projects withdrawn amounts to about 77% of all projects initiated. What is new is the increasing number of projects initiated, corresponding increase in the total capacity of new proposed projects, and the time it takes to get approval for those that are approved. About 90% of the proposed projects are solar, wind, and storage projects.

     Intermittent wind and solar in particular are likely to disrupt local power grids and make it harder to balance them. Power engineers must study them to figure out how to integrate them and what grid upgrades are needed. There are not enough power engineers to study the myriad projects in a timely manner. System operator PJM hopes to speed up the queuing process by bundling projects. PJM also announced a freeze on new applications until 2026 so they can catch up. They currently have 2700 projects under study. The workflow from interconnection request begins with feasibility, then system impact, then facilities. At any point in this process the request may be withdrawn or the system operator or other regional authority may offer an interconnection agreement so the project can be built. If transmission upgrades or other upgrades are deemed to be required, the developer will often be asked to pay the costs which leads to lots of withdrawals. Since about 2016 the average time it takes from getting an interconnection agreement to commercial energy generation is a little over 2 years.  

     At the end of 2021 more than 8100 projects were awaiting approval, up from 5600 at the end of 2020. Wind, solar, and battery projects fell 16% in 2022, partially due to queue problems. One renewables developer called it the number one project killer. As time goes by higher materials costs, which has been the trend in the past couple of years, can make new projects unviable. Queue holdups are causing major headaches for renewables developers.

     One of the biggest problems is simply that there is not enough grid and transmission capacity available and the costs to upgrade sink the projects. Developers may estimate costs, including grid upgrades, and then find out after review that those costs will be much higher than they predicted. The grid system operators sometimes must shift their costs when projects are withdrawn when evaluating subsequent projects on the same local grid. To complicate matters some developers will submit multiple projects hoping to piggyback off of projects by other developers who pay for grid upgrades. They only intend to build some of those projects at all if someone else does the upgrades. Apparently, this kind of speculative bidding is happening more and more. Rob Gramlich, president of the consulting group Grid Strategies, suggested that these perverse incentives are a consequence of a process that is too chaotic and not fair to all. It certainly seems inefficient. He thinks the grid operators should come up with upgrades that would be broadly beneficial and spread the costs over more developers and users. This approach has been successful in developing transmission for growing wind development in Texas and in the Midcontinent. The biggest problem isn’t engineering but who pays, said a MISO system planner.

     Data indicate that state incentives and mandates also contribute to the problem. In some places they have resulted in large increases in proposed small-scale solar projects that may be harder to sort out in terms of grid integration. Indeed, looking at the Berkeley Labs data, one can see that solar projects are the most numerous. In 2021, the number of proposed storage projects exceeded the number of proposed wind projects for the first time. I am guessing storage projects are easier to integrate in general since they can alter charging and discharging times to a certain extent. The whole mess does not bode well for a renewables revolution or for fast decarbonization scenarios. There has also been an increase of hybrid projects: solar-plus-storage and wind-plus storage. The Berkeley Labs study concludes:

 

“Solar (676 GW) accounts for >65% of all active generator capacity in the queues, though substantial wind (247 GW) and gas (75GW) capacity is also in development. Over 77 GW of offshore wind is currently active in the queues.”  

 

“Considerable standalone (213 GW) and hybrid (~208 GW1) battery capacity is in development, along with 7 GW of other storage.”

 

If that capacity is weighted to actual production potential by multiply by avg. capacity factors, then we get 168GW for solar, 97GW for wind, and 43GW for gas, or 54% solar, 31% wind, and 14% gas, excluding storage. The 14% represented by gas is the easiest to integrate, followed by the 31% for wind. The majority, the 54% represented by solar is the most difficult and costly to integrate. Thus, the majority of projects and potential generation is the least simple and most expensive to integrate.  

     The graph below shows the growth of proposed hybrid projects, the growth in proposed standalone storage overtaking proposed wind in 2021, and modest drops since about 2017 of proposed gas projects. It should be noted that some of those gas projects and others to be proposed will be required to backup and integrate renewables, though less so with the growth of storage, if it grows as expected.



 

Graph from the Berkeley Labs study showing capacity of different generation sources in the queue.



Graph from the Berkeley Labs study showing completion percentages by region.

 

 

     Looking at the graph below I am surprised by the amount of solar in the PJM regions considering that the region is not ideal for solar energy production. The Southeast and SPP regions have much better solar potential than PJM. However, it appears that the SPP region has only about a one fourth of the amount of solar in the queue in recent years than PJM and the Southeast has only about one third as such solar as PJM. It doesn’t seem to make sense that so much solar is being proposed in a region where solar will be less profitable due to lower capacity factors. Perhaps it is partially due to more power needs in the region due to population. PJM generally has quite a bit of reserve capacity now but that is expected to change as more thermal resources retire. Other regions with better solar and wind resources tend to be in less populated areas in the U.S. requiring more large and expensive transmission projects, unfortunately. PJM just reported that they expect 40GW of generating capacity, 90% of it from coal and gas, to retire by 2030, or 21% of the region’s total capacity. That could account for some of the uptick in solar and storage proposals. However, in the same report they noted just 15-30GW in new capacity is expected by 2030. If that is true it will eat into their reserve capacity. MISO region is facing a similar issue and the North American Electric Reliability Corporation is warning that planned retirements may have to be scaled back if reliability is to be maintained. Transmission and other grid upgrades really have to precede any new surges of renewable power. They warn that the pushes to replace fossil fuel and nuclear power could result in energy shortfalls and rolling outages in extreme weather events as we have already seen, only perhaps worse. Goals and mandates, like Biden’s goal of 100% carbon free electricity by 2035, just a little over a decade away, make reliability problems more likely, they argue.  

 


Graph from the Berkeley Labs study generation sources in the queue by region.

 

 References:

The U.S. Has Billions for Wind and Solar Projects. Good Luck Plugging Them In. Brad Plumer. New York Times. February 23, 2023. The U.S. Has Billions for Wind and Solar Projects. Good Luck Plugging Them In. (yahoo.com)

Queued Up: Characteristics of Power Plants Seeking Transmission Interconnection as of the End of 2021. DOE. Office of Energy Efficiency & Renewable Energy. PowerPoint Presentation (lbl.gov)

Largest U.S. grid operator warns of coming power capacity shortfalls. Seeking Alpha. February 25. 2023. Largest U.S. grid operator warns of coming power capacity shortfalls (msn.com)


No comments:

Post a Comment

        Apparently, the Trump administration is planning to decommission NASA satellites involved in important science missions. This may ...